Engineering practice · topic F6 · 30 hours
System integration & field commissioning
Between «runs in the lab» and «works in the field» lie weeks. Integration skill is the most underrated hard skill.
What to learn
- Integration order: single module → pairwise interfaces → subsystems → whole machine
- Controlling field variables: environment, power supply, network, floor material
- Delivery checklist and acceptance criteria (who signs, judged by what)
- Rollback plan: how to recover within ten minutes of a bad change
The lesson · plain words
System integration is the last mile from «every module works on its own» to «the whole machine runs», and the most grinding stretch: modules that are all green in unit tests will fight once assembled. This page covers the discipline of bring-up.
Five bring-up levels: never enter the next until this one is green
Look at the figure's five levels: power → comms → drives → sensors → closed loop. Each level has explicit acceptance criteria (voltage ripple, heartbeat frequency, encoder counts, frame rate, unloaded jogging). Skipping levels = two unknowns fighting — you do not know which one to fix.
Leave one «one-click self-check» command per level (a script printing PASS/FAIL) and rerun them in order after any field reboot. This one discipline cuts field troubleshooting from half a day to half an hour.
Interactive figure · drag it and see
Safety nets land first
E-stop, limit switches, and software clamps must be in place before «closed-loop bring-up» — they are the safety rope for all debugging that follows. The first power-up must support one-key disable; the first motion must happen at 10% of the clamped speed.
Field troubleshooting priority: safety first, then power, then comms, and only then algorithms. Reversing the order usually costs you a board or an injured hand.
Documentation discipline during integration
Three tables travel with the code: wiring table (which device into which port), parameter table (each node's key parameters and defaults), version table (firmware/code version of every module). Swap a sensor model in the field without a wiring table and you are doing archaeology.
Log discipline: collect whole-machine logs centrally (D3's journalctl + ROS log), timestamped and aligned. Post-mortem analysis depends on «what every module was doing at the same moment»; scattered logs are as good as none.
How deep to go
You can write a bring-up checklist (five levels + criteria + self-check commands); build one-key disable and software clamps; and complete a first bring-up on a new machine by the discipline. The market premium for systems integration engineers comes precisely from this replicable discipline.
Three questions — do you really get it?
1. What is the main risk of skipping bring-up levels (say, tuning the closed loop directly)?
- ASlower progress
- BSeveral unknowns coupled together — you cannot localize which level is at fault
- CNo risk
Show answer
B. Each level is verified independently before the next, so faults stay unit-localized.
2. At what stage should limit protection and software clamps be in place?
- ARetrofitted after all tuning is done
- BBefore closed-loop bring-up
- CBefore delivery
Show answer
B. They are the safety rope of the debugging stage. They must be active before the first motion.
3. What is the correct priority order for field troubleshooting?
- AAlgorithm → comms → power
- BSafety → power → comms → algorithm
- CWhatever comes to mind
Show answer
B. Check bottom-up. The algorithm is the last thing to suspect (F5's principle: suspect the most probable first).
Keep going deeper
Links without a marker stay on this site; the rest point to the Chinese edition until its translation batch lands.
How it fails in the field
- Starting integration at the whole-machine level; when something breaks, nobody knows whose fault it is and you eliminate modules one by one
- Field parameter changes with no record; back at the office nothing can be reproduced
You have learned enough when